Following agreements concluded during Vs. Visit 01/08/07 c / o
Ns. There seat pass for regular order
Instrumental for plant intake at Silcotub of fumes Zalau Supply and assembly "turnkey" of a plant electro -Romania, as briefly described below:
-Laying-line electric festoon and links to jb hood and side drive
- Electric plant hood (2 engines + 2 stops)
Power-supply cables for electrical connection under-hood (laying TENARIS
- Supply pulsantera local hood (laying Tenaris)
- Supply-control cabinet full TP370
- Laying electrical panel
- Electric plant as a framework to all users in The field
- Instruments PI102, 102.1, 102.2, 103.1, 103.2, LE104, LSLL104, FSL102, FSL103, LSHL108, laying directly on the electrical process
- Tools PDI102, PDI105 Laying and connecting pipe with copper 6 / 8 And fittings (development liaison about 2mt).
 
Management hood mobile:
- Electromechanical controls (teleinversione) incorporated into the main
- Buttons local league allu. Preforated with selector chaive LOC-0-DIST and 2 buttons for movement hood (command not ritentivo)
- Local keyboard-laying by Tenaris depending on the operational requirements of plant
- Festoon-line electricity supply and laying up to JB based hood
- Electrical cables from overview to pulsantera and JB HE supply and installation Tenaris
 
 Roads cables:
- Buried in the corrugated PVC is a framework and fan pumps and 2 skid
- Air for other users minors
- Fan-cockpit side pocket with output cables
- In sock-metallic sheath for users 400 VAC
- Wiring for free + gland metal for instrumentation
 
Buttons local league allu. Preforated for command ventillatore with key LOC-0-REM, button march, arrest, mushroom emergency
 
Software PLC made in accordance with the requirements Tenaris for interfacing via Ethernet with the central hall, where you see a synoptic planting.
 
Production of electrical cables and conductors after numbering cables and conductors as wiring diagrams.
Earthing AE You installed in compliance with the rules in force
 
All realized under ns. Specifications attached at Tenaris specifications and requirements Tenaris / Silcotube
 
PRICE TOTAL BODY TO FIXED AND INVARIABILE:
57.850,00 (Euro fifty seven thousand eight hundred fifty / 00)
 
ASSISTANCE:
Assistance including starting up of acceptance is also including technical assistance of the soft start for a period of about 2 days. Including travel and subsistence.
STORAGE:
For unforeseen reasons could require a storage and conservation provision c / o Vs. Workshop, instead covered for a period max. For 3 months. This provision is included to be considered in the order.
 
CONDITIONS AND VALIDITY RATES:
The total value of the individual and its component are fixed and not subject to any revision, even if caused by any increases in the cost of materials or labor, until all obligations undertaken by the supplier in the face of the order.
 
YIELD MATERIALS: Franco Silcotub - Zalau-Romania, installed in place
 
DELIVERY:
- Electric: 20/10/07 (date of testing at Calusco BG)
- End-assemblies: 10/11/07
- Starting house: 15/11/07 (subject to penalty)
 
PENALTY:
If the delivery dates established in order not to be respected, including the execution of documentation, HASCON will have the option of applying a penalty equal to 1% for every week of delay in delivery with relief 7 days. Up to a max for 10% of the total value of the order, unless further damage. The provision shall be deemed completed until the delivery of detail and final documentation.
 
PAYMENTS:
- € 37.500,00 share el framework. A positive test at Vs. Workshop with BB60 gg.dffm
- € 18.315,00 share - assembly plant to test positive with BB 90 gg.dffm
- € 2.035,00 share completion testing positive to work with BB120 days. Dffm
 
WARRANTY:
It will have a duration of 18 months after the entry into operationof the plant, max 24 months from date of delivery.
 
DOCUMENTATION:
- How specification n.6427-E-50 attached
The documentation is required in ITALIAN / ENGLISH, No. 2 paper copies + 1 copy in electronic format on CD, and should be sent c / or ns. Offices to ca Mrs. Marson. Documentation is an integral part of this order and, in the case of delays, payment of the invoice begin from the date of receipt thereof.
 
ANNEXES, PARTIES INTEGRANTI OF THIS ORDER:
- General instructions n.1 rev.2
- Specify n.6427-E-01 electrical loading list
- Specify n.6427-E-02 instrument list
- Specify n.6427-E-04 instrument data sheet
- Specify n.6427-E-10 hearting net specification and layout
- Specify n.6427-E-11 hook-up sketch
- Specify n.6427-E-12 functional description
- Specify n.6427-S-01 P & I
- Specify n.6427-G-02 Lay-out hood
- Specify n.6427-G-03 Lay-out filter
- Specify n.6427-E-50 Piano delivery documents
- Specify n.6427-E-100 list documents
- Specify n.6427-C-04 foundation drawing
- Specify Tenaris n.IT003 specific imp. Electric
- Specify Tenaris n.IT004 documentation el. And automation
- Specify Tenaris n.IT005 realization imp.el. And related testing
 
THIS ORDER WITH RELATED ANNEXES, WE MUST

Mai multe recenzii despre www.shvoong.com
www.shvoong.com        2007 
Vă rugăm evaluaţi acest rezumat : 1 2 3 4 5


Read Free Summaries - Write and Get Paid

Summarize Human Knowledge on Shvoong. Join us!

------